Final piping checklist – Goulds Pumps 3600 - IOM User Manual
Page 33
Advertising

Installation
Checklist
Check
Explanation/comment
Checked
Check that the minimum flow for
–
each component is 1 gpm (4 lpm).
If the bearing and seal chamber
cover cooling are provided, then
the auxiliary piping must flow at 2
gpm (8 lpm).
Check that the cooling water pres- –
sure does not exceed 100 psig
(7.0 kg/cm
2
).
Final piping checklist
Check
Explanation/comment
Checked
Check that the shaft rotates
Rotate the shaft by hand. Make
smoothly.
sure there is no rubbing that can
lead to excess heat generation or
sparks.
Re-check the alignment to make
If pipe strain exists, then correct
sure that pipe strain has not
the piping.
caused any misalignment.
Model 3600, API 610 8th, 9th, 10th & 11th Editions (ISO 13709) Installation, Operation, and Maintenance Manual
31
Advertising