Cv 3171 installation and operation checklist – Goulds Pumps CV 3171 - IOM User Manual
Page 14

14
CV 3171 IOM 05/11
UNCRATING/DESKIDDING
Care should be taken when uncrating or
deskidding pumps. If shipment is not delivered in
good order, and in accordance with the bill of
lading, note the damage or shortage on both the
receipt and freight bill.
Make any claims to the transportation company
promptly. Instruction sheets as well as the
instruction book for the pump are included in the
shipment.
CV 3171 Installation and Operation Checklist
COMPLETE INITIAL
DESCRIPTION
SECTION NO.
Installation Manual Received and Read
ALL
Level Pit Opening
3
Level Support Plate
3
Check Motor Rotation ---CW ---CCW
3
Install Coupling
3
Rough Alignment Completed
3
Piping Installed and Alignment Rechecked
3
Flush or Grease Piping Connected
4
Impeller Clearance Set ______ Inch
4,5
Pump Shaft-Free Turning
4
Float Controls Understood
4
Bearing Types and Lubrication
4
Coupling Guard Installed
4
Discharge Valve Partially Open
4