Grout the barrel or sub-base – Goulds Pumps VIC - IOM User Manual

Page 18

Advertising
background image

Install the barrel or sub-base on a concrete foundation

CAUTION:
You must earth (ground) all electrical equipment. This applies to the pump equipment, the driver, and any
monitoring equipment. Test the earth (ground) lead to verify that it is connected correctly.

1. Remove water and debris from the anchor bolt holes and sleeves before you start the grout.
2. For sleeve-type bolts, fill the sleeves with packing or rags in order to prevent grout from entering the

sleeves.

3. Carefully lower the barrel or sub-base onto the foundation bolts and hand-tighten the bolt nuts.
4. Use a machinist's level in order to level the barrel or sub-base or a machine surface of the discharge

head using leveling wedges.
In order to ensure an accurate reading, check that the surface being leveled is free from all
contaminants, such as dust.

1

2

3

4

5

6

7

1.

Barrel flange or sub-base

2.

Levelling wedges

3.

Floor sleeve (optional)

4.

Foundation

5.

Dam

6.

Grout

7.

Centerline anchor bolt

5. Level the barrel or sub-base in two directions at 90° on the machined surface.

Table 3: Levelness tolerances

Commercial

API

0.005 inches per foot (0.127 mm per meter)

0.001 inches per foot (0.025 mm per meter)

Grout the barrel or sub-base

Non-shrink grout is recommended for this procedure.
1. Inspect the foundation for dust, dirt, oil, chips, and water.
2. Remove any contaminants.

Do not use oil-based cleaners since they do not bond well with grout. Refer to the instructions from
the grout manufacturer.

3. Build a dam around the foundation.
4. Thoroughly wet the foundation.
5. Pour grout to a minimum thickness of 0.375 in. (9.520 mm) between the barrel or sub-base and

concrete foundation, up to the level of the dam.

6. Remove any air bubbles from the grout as it is poured by either puddling, using a vibrator, or

pumping the grout into place.

7. Allow the grout to set at least 48 hours.

Installation (Continued)

16

Model VIC Installation, Operation, and Maintenance

Advertising