Installation, Preinstallation, Inspect the sub-base – Goulds Pumps VIT - IOM User Manual

Page 17: Concrete foundation requirements

Advertising
background image

Installation

Preinstallation

Inspect the sub-base

1. If an optional sub-base is furnished, remove it from the pump discharge head when it is shipped

assembled.

2. Completely clean the underside of the sub-base.

You might need to coat the underside of the sub-base with an epoxy primer which you can purchase
as an option.

3. Remove the rust-preventative solution from the machined topside with an appropriate solution.

Concrete foundation requirements

Requirements

Make sure that you meet these requirements when you prepare the pump foundation:

• The foundation must be able to absorb any vibration.
• The foundation must be able to form a permanent and rigid support for the pumping unit.
• The foundation must be of adequate strength to support the complete weight of the pump and driver,

plus the weight of the liquid that passes through it.

Typical installation

A typical installation has these characteristics:

• Bolts with a pipe sleeve that is two and a half times the size of the bolt diameter embedded in the concrete
• Properly sized
• Located in accordance with the dimensions given in the example drawing
• Enough space inside the pipe sleeves to allow the final position of the foundation bolts to align with

the holes in the sub-base flange

1

2

3

4

5

6

1.

Sub-base, or discharge head base flange

2.

Foundation

3.

Sleeve

4.

Dam

5.

Shims

6.

Anchor bolt

Figure 3: Example of a typical installation

Installation

Model VIT Installation, Operation, and Maintenance

15