Figure 9a: Recommended MPC Minimum Piping - Single Boiler Application
NOTES:
1. All piping is schedule 40.
2.	 Pipe	sizes	listed	are	based	on	a	20°F
	
or	40°F	Delta	T	(temperature	rise	
across	the	boiler).
Select one to match application.
3. When specified supply/return piping
size	is	less	than	4”,	install	appropriate	
size	reducer	directly	onto	boiler	supply	
and	return	manifolds.
4. Drain valve - ball valve preferable,
gate	valve	acceptable	alternative	
(supplied	by	others).		Minimum	valve	
size	per	ASME	Code	is	3/4”	NPT.
5. Swing joints may be piped over the top
of the boiler if space is limited.
6. System design must accommodate the
above Boiler Operating Requirements.
7. Diaphragm expansion tank shown, but
other	types	of	air	elimination	systems	
may	be	used.
Boiler
Model
Supply / Return
20°F Rise
40°F Rise
Nom. I.D.
(Inch)
Water Side
Press. Drop
(Ft/Wtr)
Flow 
Rate 
(GPM)
Nom. I.D.
(Inch)
Water Side
Press. Drop
(Ft/Wtr)
Flow 
Rate 
(GPM)
MPC4
2
1.9
42.4
1½
0.9
21.2
MPC5
2
2.6
65.2
1½
1.6
32.6
MPC6
2
3.3
83.7
1½
2.3
41.9
MPC7
2½
4.0
102.3
1½
3.0
51.2
MPC8
2½
4.7
120.9
2
3.7
60.5
MPC9
3
5.4
139.6
2
4.4
69.8
MPC10
3
6.1
158.1
2
5.1
79.0
MPC11
3
6.8
176.7
2
5.8
88.3
MPC12
3
7.5
195.2
2½
6.4
97.6
MPC13
4
8.2
213.8
2½
7.1
106.9
MPC14
4
8.9
232.3
2½
7.8
116.1
MPC15
4
9.6
250.9
2½
8.5
125.5
MPC16
4
10.3
269.5
3
9.2
134.8
MPC17
4
11.0
288.1
3
9.9
144.1
MPC18
4
11.7
306.6
3
10.6
153.3
1
Boiler Operating Requirements:
• Minimum Return Water Temperature = 80°f
• Maximum Delta T = 80°f
• Minimum supply Water Temperature = 130°f