Shutdown procedure – JLG 340AJ Operator Manual User Manual

Page 51

Advertising
background image

SECTION 4 - MACHINE OPERATION

3121258

– JLG Lift –

4-3

2. After engine has had sufficient time to warm up, shut

engine off.

3. Turn SELECT switch to PLATFORM.

4. From Platform, pull POWER/EMERGENCY STOP switch

out, then push the ENGINE START switch until engine
starts.

NOTE:

Footswitch must be in released (up) position before
starter will operate. If starter operates with footswitch in
the depressed position, DO NOT OPERATE MACHINE.

Shutdown Procedure

IF AN ENGINE MALFUNCTION CAUSES AN UNSCHEDULED SHUT-
DOWN, DETERMINE THE CAUSE AND CORRECT IT BEFORE RESTART-
ING THE ENGINE.

1. Remove all load and allow engine to operate at low

speed for 3-5 minutes; this allows further reduction of
internal engine temperature.

2. Push POWER/EMERGENCY STOP switch in.

3. Turn Platform/Ground Select switch to Off.

Refer to Engine Manufacturer’s manual for detailed informa-
tion.

Fuel Reserve / Shut-Off System (Gas or Diesel
Engines Only)

The Fuel Shutoff System senses when the fuel level is getting
low and automatically shuts the engine down before the fuel
tank is emptied.

Depending upon machine setup, the machine will either
keep the engine shut down until the fuel tank is refilled or the
operator will be able to restart and run the engine for an
additional minute. After 1 minute, the engine will shut off for a
second time and the machine will return to the engine shut-
down mode until the fuel tank is refilled.

Advertising