General -9, Daily walk-around inspection - sheet 2 of 3 -9, General – JLG 510AJ Operator Manual User Manual

Page 31

Advertising
background image

SECTION 2 - USER RESPONSIBILITIES, MACHINE PREPARATION, AND INSPECTION

3121179

– JLG Lift –

2-9

GENERAL

Begin the "Walk-Around Inspection" at Item 1, as noted on
the diagram. Continue to the right (counterclockwise
viewed from top) checking each item in sequence for the
conditions listed in the following checklist.

TO AVOID POSSIBLE INJURY, BE SURE MACHINE POWER IS OFF.

DO NOT OPERATE MACHINE UNTIL ALL MALFUNCTIONS HAVE BEEN
CORRECTED.

INSPECTION NOTE: On all components, make sure there
are no loose or missing parts, that they are securely fas-
tened, and no visible damage, leaks or excessive wear
exists in addition to any other criteria mentioned.

1. Platform Assembly and Gate - Lockbolts in place.

Footswitch works properly, not modified, disabled or
blocked. Latch, stop, and hinges in working condition.

2. Platform & Ground Control Consoles - Switches and

levers return to neutral, decals/placards secure and
legible, control markings legible.

3. All Hydraulic Cylinders - No visible damage; pivot

pins and hydraulic hoses undamaged, not leaking.

4. Boom Sections/Uprights/Turntable - See Inspection

Note.

5. Boom Limit Switches - Switches operate properly.

6. Drive Motor, Brake, and Hub - No evidence of leak-

age.

7. Wheel/Tire Assemblies - Properly secured, no miss-

ing lug nuts, proper inflation (pneumatic).

8. Hood Assemblies - See Inspection Note.

Figure 2-4. Daily Walk-Around Inspection - Sheet 2 of 3

Advertising
This manual is related to the following products: