4.11 SHUT DOWN AND PARK

1. Drive machine to a reasonably well protected area.

2. Be sure the main boom is fully retracted and lowered

over rear drive axle.

3. Remove all load and allow engine to operate 3-5 min-

utes at LOW setting to permit reduction of internal
engine temperatures.

4. At Ground Controls, turn KEY SELECT switch to OFF.

Push in the Emergency Stop. Remove key.

5. If necessary, cover Platform Control console to protect

instruction placards, warning decals and operating con-
trols from hostile environment.

4.12 LIFTING AND TIE DOWN

Lifting

1. Refer to the Serial Number Tag, call JLG Industries, or

weigh the individual unit to find out the Gross Vehicle
Weight.

2. Place the boom in the stowed position.

3. Remove all loose items from the machine.

4. Properly adjust the rigging to prevent damage to the

machine and so the machine remains level.

Tie Down

WHEN TRANSPORTING THE MACHINE, THE BOOM MUST BE FULLY
LOWERED INTO THE BOOM REST.

1. Place the boom in the stowed position.

2. Remove all loose items from the machine.

3. Secure the chassis and the platform using straps or

chains of adequate strength.