SECTION 4 - BOOM & PLATFORM

3121234

– JLG Lift –

4-3

c. Remove hardware from the sheave pin; remove

pin and sheave from cylinder.

9. Remove hardware which secures the wear pads to

the front of base boom section; remove wear pads
from the top, sides and bottom of the base boom
section.

10. Using an overhead crane or suitable lifting device,

remove mid and fly boom sections from base sec-
tion. Note: When removing mid and fly boom sec-
tions from base boom section, retract wire rope
must be dragged along with boom sections.

11. Remove hardware which secures the wear pads to

the aft end of mid boom section; remove the wear
pads from the top, sides and bottom of the mid
boom section.

12. Remove hardware which secures the sheave guards

and sheave assemblies to mid boom section,
remove sheave assemblies from mid boom section.

13. Remove hardware which secures the wear pads to

the front of mid boom section; remove wear pads
from the top, sides and bottom of the mid boom sec-
tion.

14. Using an overhead crane or suitable lifting device,

remove fly boom section from mid section. Note:
When removing fly boom section from mid boom
section, retract wire rope must be dragged along
with fly boom section.

15. Remove hardware which secures the wear pads to

the aft end of fly boom section; remove wear pads
from the top, sides and bottom of the fly boom sec-
tion.

16. When removing wire rope from fly boom section,

push the cable into fly boom. Route wire rope back
through holes in the side of the fly boom section.

Figure 4-4. Disassembly of Sheave Assembly