4 base and boom/jib alignment, 4 base and boom/jib alignment -5 – JLG X550AJ Operator Manual User Manual

Page 49

Advertising
background image

SECTION 4 - MACHINE OPERATION

3128791

– JLG Lift –

4-5

side of machine, near the electric engine to the OFF
position. ( symbol is ON - O symbol is OFF).

6. Switch the ON/OFF switch on the lithium-ion battery

pack to the OFF position when shutting down at the
end of a work period. (0 symbol is OFF, 1 is ON)

NOTE: At low temperatures start the motor and let it run for a

few minutes, so that the hydraulic oil circulates and
reaches at least 50°F (10°C) before operating the plat-
form.

4.4 BASE AND BOOM/JIB ALIGNMENT

The machine has two reflectors/photocells that check if the
boom assembly is completely lowered and retracted, the jib is
lowered, and the turntable is aligned with the base. (see pho-
tos)

When these conditions are met this symbol will
display in position (6) on the Platform/Remote
Control LCD display.

UNLESS THESE CONDITIONS ARE MET, DRIVE, STEER,
TRACK WIDTH ADJUSTMENT, AND OUTRIGGER MOVE-
MENT IS PREVENTED.

Base/Boom Alignment - Visual Indicator

Boom/Jib and Base Alignment - Reflectors/Photocells