21. Locate connecting rod (item 10 in diagram #4) and the two connectors (item 1 in diagram

#4). Install the rod in between by flowing diagram #4. Make sure the rod is in rod guides

under the deck. Adjust connectors to take the slack out of the rods. The rods should remain
free enough to move with no slack. Do not tighten connectors or lock nuts at this time.

22. Locate the two long rods (item 5 in diagram #4) and remove one end from each rod and

slide off the eye bolt (item 4 in diagram #1). Install the eye bolt on the middle of each
crossbeam with the M10 nuts.

23. Attach short rods (item 7 in diagram #4) on the T shape lock on the bottom of the T and

hand tighten. Slide long rod through the eye bolt and attach on end to the top side of the

T. Install the other sides of the rods on each safety lock lever (see item 8 in diagram #7).
Do the same on the other crossbeam. Before tightening, ensure each of the T-rods are
oriented in a vertical manner. Tighten all jam nuts.

24. Tighten the jam nuts on the handle rod and the T rod.

25. Finally, adjust and tighten the rod connectors under the deck, and tighten the jam nuts

against the connectors.

26. Fill oil tank with three gallons of ISO32 hydraulic oil. Install breather (black) on top of of

the oil tank, and put cap (red) on the bottom of tank (DO NOT DRILL OIL TANK).

27. Final adjustments: Check all cables and make sure they are all in their pulleys. Press up

button on the power Unit and let fluid pump into the cylinder. Once the lift is raised off the
locks, release the up button and pull the safety lock release handle to disengage all locks
and then lower the lift with the lowering lever on the power unit (locks must be disengaged
while lowering). Keep holding decent lever for seconds after the lift reaches its bottom

position to let air escape.

28. Raise the lift up by about 10’’. Measure the height of the crossbeam at each column to

determine the highest point. Adjust the cable on the highest point column until at least 3
threads pass through the nylock nut. Then adjust the other three cables to match this

height to ensure the runways are level.

29. Raise the lift until you hear each column lock “click” into position. Using the down lever

only, allow the runways to sit into the locks. Measure each corner of the runways and

adjust the lock ladder accordingly to ensure level.

30. Operate the lift with a vehicle. Raise and lower the lift three times. Confirm all the

operational functions, equalizing cables and safety lock work well.

NOTE:

FOR ANCHOR BOLTS INSTALLATION PLEASE SEE NEXT PAGE.