FOUNDATION and ANCHORING REQUIREMENTS:


Lift should only be installed on level concrete floors with no
more than 3º of slope and a minimum of 4 inches (102mm) and
3000 psi (20.7MPa) concrete that has been aged a minimum of
30 days. A qualified person should be consulted to address
seismic loads and other local requirements.
Do not install the lift on asphalt or outdoors.

Maintain a 6’’ minimum distance from any slab edge or seam.
Hole depth should be a minimum of 4’’.


When use shims, MAKE SURE shim thickness not exceed 1/2’’
when using the anchors with the lift.