MTS Acumen Electrodynamic User Manual

Page 37

Advertising
background image

5. Remove the fixed wood blocks around the machine.

6. Use the packing list to inventory all the boxes. Accessories can be in the container with the load frame or

can be packaged separately. Do not open any of the packing boxes. The packing list will indicate the total
number of boxes that are included in the shipment. Count the number of boxes you received to make sure
you have the correct number of boxes. Except for the "Open This Box First" box, do not open these boxes
until the field service engineer arrives to install your testing system. This ensures that no parts are lost
prior to installation.

7. If a crane is used to move the load frame, secure the two hoist rings at the indicated lift points. Ensure

the hoist rings are screwed completely into the threaded holes and tightened securely. Use the crane to
slowly and carefully lift the frame clear of the wooden pallet, and place it in its operating position..

8. If a forklift is used to move the load frame, lift the load frame under the crosshead and slowly move the

load frame to its table.

9. Retain all packing materials until the system is satisfactorily installed and all parts, assemblies, and

accessories have been located.

10. When the frame is in its operating location, you can proceed with the installation process.

MTS Acumen™ Electrodynamic Test System 37

Moving the Frame