Assembly..... continued – Schwank Parasol Series Post Mount User Manual

Page 10

Advertising
background image

4SN/L5,4BN/L6 Manual

IM080630

RD: JUNE 2008

RL: 1A

BA

If placing on concrete patio only:

Drill 3 holes 1 3/4” deep using the 3/8” ma-
sonry drill bit (not supplied). Insert the 3 x
3/8” lag bolts provided, tapping them in using
the hammer shaft until the washer stops it at
the floor. Tighten the nuts down tight and the
stud threads will get longer.
Remove the nuts and washers, leaving 3 x
threaded studs sticking out of the concrete.

ASSEMBLY..... CONTINUED

Bolt 3 bolts down into the ground to secure
heater into place through the opening on the L-
shaped stabilizers.

Check that the center post and the burner as-
sembly stand vertically as shown.
Make sure all bolts and nut pairs are tightened.
Ensure correct connection by local gas profes-
sional.

Page 7

Advertising