Schwank STSp-USA User Manual
Page 17
SP-MSTP-AU-05A
STS-p Manual
RD: DEC, 2003
RL: 5
KH
TABLE 4
MODEL
TURBULATOR LENGTH
(IF REQUIRED)
STS-p 200-70/60/50
10’
STS-p 175-70/60/50
10’
STS-p 155-60
not required
STS-p 155-50
not required
STS-p 155-40
10'
STS-p 130-50
not required
STS-p 130-40
10'
STS-p 130-30
14'
STS-p 110-50
not required
MODEL
TURBULATOR LENGTH
(IF REQUIRED)
STS-p 110-30
14'
STS-p 80-40
10’
STS-p 80-30
14'
STS-p 80-20
14'
STS-p 60-30
14’
STS-p 60-20
14'
STS-p 45-20
5’
STS-p 45-10
5’
STS-p 110-40
10'
Where required the STS-p Series Heaters will be supplied with the turbulators, factory
installed into the end tube(s) of the system configuration.
NOTE:
5 90
0
(shown) or 180
0
Elbow
6 Point at which Swaged tube is fully
inserted into elbow and Swaged end of
elbow is fully inserted into tube.
1 End-Plate-Hanger
2 Reflector
3 Hanger Flange OVER Reflector
4 Tube Coupler
1
3
3
2
2
5
4
6
FIGURE 12 PLATE HANGER/ELBOW INSTALLATION
Page 13