LEAK TEST:

Now that the heater is assembled, for your safety you must perform
a leak test of all connections and hoses,

Mix equal parts of water and soap, brushing mixture on all joints.

1. Ensure that the heater gas control knob is fully closed by turning
completely clockwise.
2. Open gas valve
3. Apply the soap solution generously to all connections and hoses.

If you detect bubbles, there IS a leak. Close gas valve completely.

Retighten the leaking connection and repeat leak test process, until
ALL leaking has ceased, no matter how small.
If the leak cannot be repaired permanently, close the gas valve completely
and contact a qualified and licensed gas technician.

Connect the Natural Gas supply line to the flexible hose at
the base of the pole as per gas code.

A 5” w.c. Gas Pressure Regulator is required (not supplied)

after the shut off valve to each heater or zone.

6. CONNECTION AND TESTING:

Page 8

NATURAL GAS CONNECTION:

PROPANE CONNECTION:

Connect the Propane Gas supply line to the flexible hose at
the base of the pole as per gas code.

A 10” w.c. Gas Pressure Regulator is required (not sup-
plied) after the shut off valve to each heater or zone.