Electrical Supply and Load
Connections

Electrical termination hardware is supplied with each system. One box contains
all needed hardware for one system installation. The box is labeled:

The incoming 3-phase electrical service and outgoing load cables enter through
the top of the switchboard enclosure and connect to the appropriate bus
locations. To access the main electrical terminals:

1.

Remove the CABLE ENTRY PLATE on the top of the switchboard

2.

Open the two right side doors of the switchboard

3.

Remove the dead front panel covering the circuit breakers (4 screws)
(Refer to

Figure 4

). Remove the transparent shield

The cable entry plate may be fitted for conduit or cable ladder as needed. The
other top panels may also be removed if needed. All panels must be replaced after
installation. Locations of the main electrical terminals are shown in

Figure 5

and

Figure 6

.

Figure 4 - Switchboard covers