Receiving

1.

Upon delivery of the motor control center, inspect the shipment for lost
items and any damage that may have occurred during transit. Refer to
the packing slip for a list of items included in the shipment. If the
package appears to be damaged, unpack the equipment for further
inspection.

2.

In the event that there is evidence of loss or damage, the buyer must
follow the procedure outlined below:

• Note on the delivery receipt that the equipment being received is

damaged.

• Contact the carrier that made the delivery and schedule an

inspection.

• Inform your local Rockwell Automation representative that the

equipment is damaged.

• Retain all product packaging for review by the carrier's inspector.

For further assistance, contact your Rockwell Automation representative.

IMPORTANT

Delivery of equipment from Rockwell Automation to the
carrier is considered delivery to the buyer. The carrier
becomes liable for any damage that occurs during transit. It
is then the buyer's responsibility to notify the proper party
if damage is found. The buyer may forfeit any right to
recovery for loss or damages by failing to comply with the
following steps.