3 Start-up

850 Professional IC – Cation – Prep 2

■■■■■■■■

61

3 Start-up

The chapter Start-up is divided into 2 sections:

Initial start-up

The initial start-up is carried out during the ini-
tial installation
.

Conditioning

Conditioning is carried out as a final installation
step and after each time the system is started.

3.1

Initial start-up

The initial start-up is carried out during the initial installation. The entire
system is flushed before the guard columns and separation columns are
installed.

Caution

The separation column and guard column may not be installed for the
initial start-up.

Make sure that the 6.2744.040 coupling is being used instead of the
columns.

Perform the following steps during the initial start-up:

1 Preparing the software

Start the PC program MagIC Net.

Open the Equilibration tab in MagIC Net.

Select (or create) a suitable method.

2 Preparing the instrument

Ensure that the eluent aspiration tube is immersed in the eluent
and that there is enough eluent in the eluent bottle.

Switch on the instrument.

3 Deaerate high pressure pump

Deaerate the high pressure pump(s) via the purge valve (see
Chapter 2.10.2, page 38)
.

4 Rinsing instrument without columns

Rinse the instrument (without columns) with eluent for 5 minutes.