1.3 PROBE ASSEMBLY INSTALLATION (E MODEL ONLY)

Optic Cable: 1mm core; 1/4” PFA protective tubing.

Install seal into head.

Install probe assembly into head.

Thread probe cap into head hand tight only, no tool needed.

Connect fiber optic cable to sensor. NOTE: Minimize bends in fiber optic

cable to 2” radius minimum to help ensure optimum signal strength. NOTE:
Standard cable length is 15 ft. [4.57 meters].

Figure 1-2

1.4 PLC CONTROL SCHEMATIC

Shown below is an example of the fiber optic end of stroke detection for a Maxim
Pump. The Programmable Logic Controller (PLC) control schematic shown will
allow the Maxim to be controlled by a PLC. Some of the features that can be
programmed are:

Start and stop pump

Monitoring approximate flow rate

Leak sensing

High and low flow rate detection

Preventative maintenance counter

Cycle counting

Oscillator control override

NOTE: See examples of ladder logic programs in Section 4.10.