08 manual arc (stick) setup, Manual arc (stick) setup -5, Installation arcmaster 175 te – Tweco 175 TE Arcmaster User Manual

Page 27

Advertising
background image

instaLLation

arcmaster 175 te

Manual 0-5116

3-5 Installation

3.08 Manual Arc (STICK) Setup

Figure 3-2: Setup for Manual Arc (STICK) Welding

Manual Arc Sequence of Operation
1. Switch the ON/OFF Switch (located on the rear

panel) to OFF.

2. Connect the earth clamp lead to the Negative

Output Terminal and electrode holder lead to the

Positive Output Terminal. Consult the electrode

manufacture's packaging for the correct electrode

polarity.

3. Plug the Power Source in and switch the power

switch ON.

4. Set the Process Switch to Manual Arc.
5. Set the Weld Current control to the desired welding

current.

6. Switch the ON/OFF Switch (located on the rear

panel) to the ON position. This will immediately

energize the power supply up to the output

terminals and the electrode holder.

7. Commence welding. If necessary, readjust the

Weld Current control to obtain the welding

condition required.

8. After completion of welding the Power Source

should be left turned ON for 2 to 3 minutes.

This allows the fan to run and cool the internal

components.

9. Switch the ON/OFF Switch (located on the rear

panel) to the OFF position.

230V AC POWER SOURCE

Set Welding Current
as specified by the
Electrode Manufacturer.

Set Process Selection
Switch to Manual Arc.

Positive Output
Terminal
(Dinse™ 50)

Negative Output
Terminal
(Dinse™ 50)

Art # A-08668_AB

200A

Advertising