2.5 Folding and Unfolding

2.5.1 Unfolding into the Work
Position

1. Open the machine if possible on level

ground, if this is not possible try and

orientate the machine so the drawbar

and tractor is pointing up any slope.

2. Fold down the light units and open the

inline hydraulic tap on the wing catcher

circuit (A).

3. Operate the wing circuit (yellow) spool.

This will then lower the catchers (B)

then open the wings out (C and D).

Continue to pressure the wings out

keep pumping until the wing cylinders

have reached full stroke.

When the wings are fully open they

will appear not to be parallel. This

is to enable the machine to ‘float’

over uneven ground in work and is

normal.

4. With the wings fully open (E) operate

the tilt (red) spool to lower the machine

rearwards (F). Continue to operate the

tilt spool once the working elements

have touched the ground to roll the

machine rearwards onto the DD roll

(G). NOTE: when tilting rearwards

from folded there will be a delay (5-15

seconds depending on flow) before the

machine begins to tilt. This is normal,

continue to pump oil as normal.

5. With the machine now tilted onto the

rear roll fully turn off the inline hydraulic

tap on the wing (yellow) circuit. This will

isolate the catcher arm circuit.

6. The machine is now ready to be set for

work.

Unfolding