4/9/04

1-10

113-395M

MARKER HYDRAULIC SYSTEM INSTALLATION (CON’T.)

INSTALLING: 24 or 30' DUAL MARKER HYDRAULICS

GENERAL NOTE: JIC fittings do not require high torque. JIC and O-ring fittings do not require sealant. To avoid crack-
ing fittings or castings from overtightening, DO NOT use plastic sealant tape.

REFER TO THE PICTORIAL HYDRAULIC SCHEMATIC Fig. 10 WHEN INSTALLING: 24 or 30' DUAL MARKER HY-
DRAULICS

1. Attach the 90˚ swivel elbows (#4) to the base and rod end of both marker cylinders (#3).

2. Uncoil and attach hoses (#5 & 6) to the swivel elbows (#4) attached to the marker cylinder (#3). Note that the longer
of the two hoses goes to the rod end of the cylinder. Route these two hoses through the frame member cut-outs and
hose clamp. Parallel to the hoses feeding the outer gage wheel cylinder as shown in Fig. 11 on page

1-11. Place the

hoses in the clamps later, after the free ends of the hoses are plumbed.

3. Remove the three bolts (#15) from the top of the tongue truss and install the valve mount plate (#14) under them.Re-
ferring back to schematic Fig. 10, Bolt the selector/sequence valve (# 7) to the valve mount. The valve is held in place
with bolts (#9), flat washers (#10), lock washers (#11) and nuts (#12).

4. As noted in the schematic, Fig. 10, switch the elbow and straight fittings on ports A and G of the sequence/selector
valve (#7). Do the same for ports B and J. Next, install the two elbow fittings (#13) on ports E and F.

5. Locate the two long hoses (#1) coming from the tractor, going to the fold cylinders. Break the first hose at the “T”
between the rod end of the fold cylinders, the second at the flow divider. Take these same two hoses and install them
on the selector/sequence valve (#7) ports A and B.

6. The two hoses just removed from the fold cylinders are replaced by two shorter hoses (#2). Run one from the “T”
between the rod end of the fold cylinders to port G on the top of the selector/sequence valve (#7). Run the other from
the fold cylinder's base end flow divider to the adjacent port J.

7. The last hoses to connect should be the four coming from the marker cylinders. Connect the base end hoses (#5) to
ports E and F on the selector valve (#7), and the rod hoses (#6) to ports C and D as shown.

11166

Dual Marker Hydraulic Schematic

Fig. 10