Setting up the StackLink
Remove the StackLink from the carton and carefully remove the protective plastic
covering.
Un-wrap any TrackLinks and/or StopLinks included.
Remove the Stacks from the carton, then remove the stack from the packaging
Install the supplied Stacks on the StackLink securely.
Setting up the TrackLink(s)
Position the TrackLink into either side of the StackLink and insert the track so the
groves match and fit into place (Figure 7).
NOTE: Be sure the TrackLink and StackLink gearing is properly positioned and
aligned for correct operation
Secure the track with the included Clamp Bars (Figure 11). Repeat if connecting
an additional TrackLink if required.
Secure the TrackLink to any instrument nests.
NOTE: Calibration and/or origin adjustments may need to be set for these
instruments. (I.E. PlateCrane positions, Micro10 dispensing origin, etc.)
Figure 7