Rack Installation Guide

7

Rack Stabilizer Feet

CAUTION:

Before installing systems in a rack, install front and side stabilizers on stand-alone racks or the front

stabilizer on racks joined to other racks. Failure to install stabilizers accordingly before installing systems in a
rack could cause the rack to tip over, potentially resulting in bodily injury under certain circumstances.
Therefore, always install the stabilizer(s) before installing components in the rack.

CAUTION:

After installing system/components in a rack, never pull more than one component out of the rack on

its slide assemblies at one time. The weight of more than one extended component could cause the rack to tip
over and may result in serious injury.

The stabilizer feet help prevent the rack from tipping over when a system or other component is pulled out
of the rack with the slide assemblies fully extended. See the documentation provided with the rack cabinet
for instructions on installing and anchoring the stabilizer feet.

Installation Tasks

Installing a rack kit involves performing the following tasks (described in detail in subsequent sections) in
their numbered order:

1 Removing the rack doors (if necessary)
2 Marking the rack (if necessary)
3 Configuring the sliding rail assemblies
4 Installing the mounting rails in the rack

RapidRails installation

VersaRails installation

5 Installing the system in the rack
6 Attaching the cable tray
7 Attaching the cable-management arm
8 Routing cables
9 Attaching the cable-management arm retainer

10 Replacing the rack doors (if necessary)

Recommended Tools and Supplies

A #2 Phillips screwdriver (VersaRails only)

Masking tape or a felt-tipped pen for marking the mounting holes to be used

A measuring ruler or tape measure