Figure c-7 – Cisco 3550 User Manual

Page 70

Advertising
background image

C-6

Catalyst 3550 Multilayer Switch Hardware Installation Guide

OL-6155-01

Appendix C DC Power Connections

Connecting to DC Power

Figure C-7

Inserting Wires in the Terminal Block Plug

Step 5

Use a ratcheting torque screwdriver to torque the terminal block captive screw (above the installed wire
lead) to 4.5 lbf-in. (72 ozf-in.), as shown in

Figure C-8

.

Caution

Do not overtorque the terminal-block captive screws. The recommended maximum torque is 4.5 lbf-in.
(72 ozf-in.)

Figure C-8

Torquing the Terminal-Block Captive Screws

Step 6

Repeat Steps 4 and 5 for the remaining three DC-input power source wires.

Figure C-9

shows the

completed wiring of a terminal block plug.

60532

Return
Negative

Return

Feed A

Feed B

Negative

60533

Torque to 4.5 lbf-in. (72 ozf-in.)