Thermcraft XST-3-0-36-3V User Manual

Page 223

Advertising
background image

Installation and Operation Handbook

Programmer Operation

2416 Controller

5-7

Hi’ − Deviation High Holdback holds the program back when the process variable

deviates above the setpoint by more than the holdback value.

bAnd’ − Deviation Band Holdback is a combination of the two. It holds the program back

when the process variable deviates either above, or below, the setpoint by more
than the holdback value.

There is a single Holdback Value which applies to the whole program. However, the
Holdback type and whether or not it is enabled, can be applied to the program as a whole, or
individually in each segment.

Power failure

If power is lost and then restored, while a program is running, the behaviour of the
programmer is determined by the setting of the parameter ‘

Pwr.F’ Power fail strategy in

Programmer configuration. This can have one of three settings:

− cont (Continue), rmP.b

(Ramp from PV), or

rSEt (Reset).

If

cont is selected, then when power is restored the program continues from where it was

interrupted when power was lost. All parameters, such as the setpoint and time remaining in
the active segment, will be restored to their power-down values. For applications that need to
bring the measured process value to the setpoint as soon as possible, this is the best strategy.

If

rmP.b is selected, then when power is restored the setpoint starts at (‘servos to’) the

current measured value, and then ramps to the target setpoint of the active segment at the last
ramp rate used by the program. This strategy provides a smoother recovery. The two
diagrams below illustrate the respective responses, Fig5-2 if power fails during a dwell
segment and Fig5-3 if it fails during a ramp segment.









Figure 5-2 Continue after a power fail


Figure 5-3 Ramp back after a power fail

If

rSEt is selected, then when power is restored the program terminates.

Setpoint

Ramp

Segment

Dwell Segment

Time

t1

t2

Segment dwell

time = t1 + t2

Power off

Power on

Setpoint

Ramp Segment

Time

Power off

Power on -
Servo to new PV level

Target setpoint