Series 5500 Advanced & Alternate Installation Instructions

IMPORTANT NOTE:

It is critical to allow at least a ¾” space between the perimeter of the jamb mullion and

the condition for setting space for the last frame unit to be installed.

STEP #4 INSTALL FRAME HEAD & SILL COMPONENTS

A. Set the last frame in the run into the opening, mating the filler with the intermediate

vertical until the filler and vertical snap together.

B. When the frame is set level and plumb, apply dead load shims below the verticals, and

apply anchor bolts as shown per the approved shop drawings.

DEAD LOAD

SHIMS

ANCHOR BOLTS

AS REQ’D.

‘F’ ANCHOR

‘F’ ANCHOR

PRE-ASSEMBLED

FRAME UNIT

ANCHOR BOLTS

AS REQ’D.

See Section III of the Standard

Installation Instructions , step 4 for

special sealant note at horizontals.

Section III: Alternate Anchorage Method