Disconnect power supply when wiring SS1-R failure to do so may result in personal injury and/or equipment damage.

1. All wiring from the SS1-R to the oil furnace must be appropriate Class 1 wiring as follows: installed in rigid metal conduit, inter-

mediate metal conduit, rigid non-metallic conduit, electrical metallic tubing, Type MI Cable, Type MC Cable, or be otherwise

suitably protected from physical damage.

2. Six wires are to be run from the Rheem, Ruud, Weatherking & Heat Controller oil fired furnace to the SS1-R Side Wall Vent System.

3. Drill a 1” diameter hole into the junction box side of the furnace, allowing for adequate clearance from electrical components, See

Diagram R Plan view. Use caution when drilling into furnace so existing wiring and components are not damaged. The six

wires connecting the Rheem, Ruud, Weatherking & Heat Controller oil fired furnace to the SS1-R must be routed through this

hole to the burner junction box. If electrical conduit is not going to be used, then a mechanical strain relief must be used where

wires pass into the burner junction box.

4. Remove screws that secure R8184G primary control unit to the existing junction box.

5. Remove wire nuts which secure the Orange, Black, and White wires of the R8184G primary control.

6. Remove a knock-out slug from the existing junction box. Do not use the front knock-outs.

7. Route the six field installed wires from the SS1-R terminal strip through the 1” diameter hole in the side of the Rheem, Ruud,

Weatherking or Heat Controller oil fired furnace to the existing junction box of the burner motor. A bushing is recommended for

the 1” diameter hole if metal conduit is not used.

8. Use a field installed wire and a wire nut to connect the Orange wire of the R8184G primary control to the O terminal on the

SS1-R terminal strip.

9. Use a field installed wire and a wire nut to connect the L1 terminal of the SS1-R terminal strip to the Black wire of the R8184G

primary control, the Black lead of the R1 relay contact and L1 of the existing burner junction box. R1 relay is attached to one

half of the junction box extension.

10. Use a field installed wire and a wire nut to connect the L2 terminal of the SS1-R terminal strip to the White wire of the R8184G

primary control, the White wire of the R1 relay, the White wire of the burner motor, a black lead from the oil solenoid valve, a

black lead from the ignition transformer, and L2 of the existing burner junction box. It may be necessary to use two wire nuts

and a connecting wire.

11. Use a field installed wire and a wire nut to connect the Y terminal of the SS1-R terminal strip to the remaining wire from the oil

solenoid valve.

12. Use a field installed wire and a wire nut to connect the M terminal of the SS1-R terminal strip to the Blue wire of the R1 relay.

13. Connect the ground terminal of the SS1-R to the existing ground terminal of the burner junction box.

14. Using a wire nut, connect the Yellow wire of the R1 relay contact to the Black wire of the burner motor and the remaining Black

wire of the ignition transformer.

12

DIAGRAM Q

NOTE:
All wiring connections are to be
made with wire nuts inside oil