Laars heating systems, 2f. gas supply and piping – LAARS Mighty Max HH (Sizes 320M - 1000M) - Installation, Operation and Maintenance Instructions User Manual

Page 6

Advertising
background image

Page 6

LAARS HEATING SYSTEMS

operate at high altitudes have appropriate
stickers or tags attached.

3.

The figures in Table 3 should be used to size the
gas piping from the gas meter to the boiler.
Check local codes for BTU/h capacity required.

4.

Install a sediment trap (drip leg) ahead of the gas
controls (see Figure 4). Fit the trap with a
threaded cap which can be removed for cleaning.

5.

When required by code, install a second manual
gas shutoff valve. Do not remove manual shutoff
valve supplied with the boiler.

6.

Disconnect the boiler and its individual shutoff
valve from the gas supply piping system during
pressure testing of the system at pressures higher
than 1/2 psi (3.5 kPa). Isolate the boiler from the
gas supply piping system by closing its
individual manual gas shutoff valve during any
pressure testing of the gas supply piping system
at test pressures equal to or less than 1/2 psi
(3.5 kPa).

7.

Gas supply pressures to the boiler are listed in
Table 4.

Supply Pressure

Water Column

Natural Gas

Propane Gas

in.

mm

in.

mm

Minimum

5

127

9

229

Maximum

9

229

14

356

Table 4. Gas Supply Pressure Requirements.

au systéme d’évacuation est mis à l’air libre de
façon adéquate. Remettre les portes et les
fenêres, les ventilateurs, les registres de
cheminées et les appareils au gaz à leur position
originale.

7.

Tout mauvais fonctionnement du systéme
d’évacuation commun devrait êvacuation
commun devrait être corrigé de façon que
l’installation soit conforme au National Fuel
Gas Code, ANSI Z223.1/NFPA 54
et (ou) aux
codes d’installation CAN/CGA-B149. Si la
grosseur d’une section du systéme devrait être
modifié ppour respecter les valeurs minimales
des tableaux pertinents de l’appendice F du
National Fuel Gas Code, ANSI Z223.1/NFPA 54
et (ou) des codes d’installation CAN/CGA-B149.

2F. Gas Supply and Piping

Review the following instructions before

continuing the installation.

1.

Gas piping installation must be in accordance
with the latest edition of ANSI Z223.1/NFPA 54.
In Canada, the installation must be in accordance
with CAN1-B149.1 or .2 and all local codes that
apply. See Figure 3 for boiler gas valve
arrangement.

2.

Check the rating plate to make sure the boiler is
fitted for the type of gas being used. Laars
boilers are normally equipped to operate below a
2000 foot (610m) altitude. Boilers equipped to

Distance from Gas Meter or Last Stage Regulator

0-100 feet

100-200 feet

200-300 feet

0-30m

30-60m

60-90m

Natural

Propane

Natural

Propane

Natural

Propane

Size

in.

mm

in.

mm

in.

mm

in.

mm

in.

mm

in.

mm

320M

400M

520M

625M

775M

1000M

1.25

1.25

1.50

1.50

2.00

2.00

32

32

38

38

51

51

1.25

1.25

1.25

1.25

1.50

1.50

32

32

32

32

38

38

1.50

1.50

2.00

2.00

2.00

2.50

38

38

51

51

51

64

1.25

1.25

1.50

1.50

1.50

2.00

32

32

38

38

38

51

1.50

2.00

2.00

2.00

2.50

3.00

38

51

51

51

64

76

1.50

1.50

1.50

2.00

2.00

2.50

38

38

38

51

51

64

Notes: 1. These numbers are based on 1/2 inch (13mm) water column pressure drop.

2. Check supply pressure and local code requirements before proceeding with work.

3. Pipe fittings must be considered when determining gas pipe sizing.

Table 3. Natural Gas and Propane, Pipe Size Requirements.

Advertising