4.0 Dimensions

& Clearances

(cont'd)

WARNING

Units must be level for proper operation. Do not place or add additional

weight to the suspended furnace. See Hazard Levels, page 2.

5.0 Suspending or

Mounting the

Furnace

Before installing the furnace, check the supporting structure to be used to verify that it

has sufficient load-carrying capacity to support the weight of the unit.
Service and combustion air clearances apply to both suspended and mounted heater.

Net Weight by Size

Size

75

100

125

140

170

200

225

250

300

350

400

Lbs

104

104

126

128

150

172

194

216

262

306

328

kg

47

47

57

58

68

78

88

98

119

139

149

5.1 Weights

The furnace is provided with four 15/32" (12mm) diameter holes to provide four-point

suspension. To suspend the unit, use 7/16"-16 threaded rod and the hardware shown

in

FIGURE 6A. See FIGURE 6A, right side, for details. NOTE: A hanger adapter kit

Option CK3 with swivels for 1" pipe is available. See

FIGURE 6B.

5.2 Suspending the

Furnace

Centerline of Hangers

A

16”

(406mm)

15/32” (12mm)

Diameter Holes

7/16” Diameter

Threaded Rod

Nut for 7/16” Rod

15/32” (12mm)

Diameter Hole

Hanger

Split Ring Lockwasher
Nut for 7/16” Rod

Front View

Side V

iew

FIGURE 6B - Option CK3

Hanger Kit (P/N 57959) with

four threaded sockets

Free-turning threaded

socket (1" pipe)

FIGURE 6A -

Suspending a

Single Furnace

5.3 Mounting the

Furnace

Standard position

of hanger bracket.

To base mount,

remove hanger

bracket and

re-locate to

position below.

Re-locate hanger

bracket to this

location when base

mounting heater.

Access

Panel in

Duct

Access

Panel in

Duct

Limit Control

(on discharge

side of unit)

Airflow

Combustion Air Inlet

Combustion

Air Inlet

6” (152mm)

minimum

clearance

10” (254mm)

12” (305mm) clearance

to combustibles required

from furnace bottom

Keep area clean and

maintain 29” (737mm)

clearance for burner

rack service.

FIGURE 7 -

Base-

Mounted

Furnace

Required Clearances

Front

Top

Flue Connector

Sides Bottom

Rear

6"

6"

6"

12"

12"

29"

152mm

152mm

152mm

305mm

305mm

737mm

Change position of the

hanger bracket as shown in

FIGURE 7.

When the furnace is

mounted on combustible

material, a minimum

clearance of 12" (305mm)

is required.

4.2 Clearances (cont'd)

"A"

Size

inches

mm

75-100

14-5/8

371

125-140 17-3/8

441

170

20-1/8

511

200

22-7/8

581

225

25-5/8

651

250

28-3/8

721

300

33-7/8

860

350

39-3/8 1000

400

44-7/8 1140