1 post installation tests, Post installation tests – Generac Power Systems 4270-0 User Manual

Page 37

Attention! The text in this document has been recognized automatically. To view the original document, you can use the "Original mode".

Advertising
background image

Section 3 - Post-installation Start-up Checks

QUIETPACT™ 75D Recreational Vehicle Generator

POST-

INSTALLATION
START-UP
CHECKS

3.1 POST INSTALLATION TESTS

The generator set was factory tested and adjusted.
You should not be required to adjust the unit any fur­
ther except under special circumstances.

-----A

WARNING

A-----

A

Do not make any unnecessary adjustments.

Factory settings are correct for most applica­

tions. When making adjustments, however, be
careful to avoid overspeeding the engine.

3.2

BEFORE INITIAL START-UP

Before starting, complete the following:

1. Check the engine crankcase oil level and, if nec­

essary, fill to the dipstick “FULL’ mark (cross-
hatched area) with the recommended oil. Do not

fill above the FULL mark.

2. Check the fuel supply. Fuel lines must have been

properly purged and leak tested in accordance
with applicable fuel codes. All fuel shutoff valves
in the fuel supply lines must be open.

3.3

INITIAL START

When you are absolutely certain that the unit has
been properly installed and prepared for use, start
the engine as follows:

1. Turn off all electrical loads. Do this by setting the

generator’s line breakers to their “OFF” (or open)
position.

2. Refer to Part 1, Section 2.4, “Starting the

Generator” (Page 8), for cranking and starting
instructions. The engine may require more
cranking for initial starting since the fuel lines
have to be primed (use of the preheat switch will
operate the generator’s electrical fuel pump and
shorten this time).

3. Let the engine warm up for about five minutes to

allow internal temperatures to stabilize.

4. Carefully inspect the engine/generator for fuel, oil

and exhaust system leaks. Before proceeding to the
next step, correct any leakage immediately.

5.

When all tests and adjustments at no-load are

completed, apply electrical loads and check
for proper operation under load. See Section
3.4. Run the unit at least 30 minutes with
loads applied.

6.

Turn off all electrical loads by setting the gen­

erator’s line breakers to their “OFF” (or open)
position.

7. Let the unit run at no-load for a few minutes to

stabilize internal engine/generator temperatures.
Then, shut down the engine.

NOTE:

The generator set was thoroughly tested and
adjusted at the factory before shipping. No addi­
tional adjustment should be necessary. Only

qualified service technicians who have been
trained should perform adjustments outlined in

this manual.

3.4

TESTING

UNDER

LOAD

Apply electrical loads equal to about 50 to 75 percent

of the unit's rated wattage/amperage capacity.

Let the unit run at least 30 minutes with load applied.
During this part of the test, check that the unit is not
running excessively hot and that adequate cooling air­

flow is available. 'Vbu must not allow the unit to over­
heat during prolonged operation.

NOTE:

The generator engine is equipped with a high
coolant temperature switch. The switch has normal­
ly open (N.O.) contacts. When the engine coolant

temperature is too high, switch contacts close, and
the engine shuts down automatically.

GENERAC RECOMMENDS THAT YOU TEST THE
GENERATOR FOR ADEQUATE COOLING.

Generac*

Power Systems, Inc.

35

Advertising