IMPORTANT: The dryer and its individual shut-off valve must be disconnected

from the gas supply piping system during any pressure testing of

that system at test pressures in excess of 1/2 psig (3.5 kPa).

NOTE: The dryer must be isolated from the gas supply piping system by closing

its individual manual shut-off valve during any pressure test of the gas

supply system at test pressures equal to or less than 1/2 psig (3.5 kPa).

H. PREPARATION FOR OPERATION/START-UP

The following items should be checked before attempting to operate the dryer:

1. Read ALL "CAUTION," "WARNING," and "DIRECTION" labels attached to the dryer.

2. Check incoming supply voltage to be sure that it is the same as indicated on the dryer data label

located on the back of the dryer control (service) door.

3. Check to assure that the dryer is connected to the type of heat/gas indicated on the dryer data

label.

4. The sail switch damper assembly was installed and adjusted at the factory prior to shipping.

However, each sail switch adjustment

must be

checked to assure that this important safety

control is functioning.

5. Check bolts, nuts, screws, terminals, and fittings for tightness.

6. Be sure ALL gas shut-off valves are in the open position (for GAS MODELS ONLY).

7. Be sure ALL back guard panels and service box covers have been replaced.

8. Check the lint door to assure that it is closed and secured in place.

IMPORTANT: If during installation the lint door safety chain was disconnected, it must be

reconnected or personal injury may result.

9. Rotate the basket (tumbler) by hand to be sure it moves freely.