Commissioning

You must complete, date and sign the ‘tick box’ checklist in the owner’s
warranty card. Use this copy to check the installation prior to completing the
owner’s documentation.

Unit

‰

All equipment ordered by the
customer is installed.

‰

The unit is level and secure.

‰

The water supply line has been
flushed to clear swarf and debris and
is free of leaks.

‰

The tank is free of foreign matter and
debris and the water isolating tap is
turned ON.

‰

Water drainpipe work is completed
and sealed.

‰

The water basin fills with water and
the float valve closes correctly when
the water level is 65 -75mm from the
bottom of the tank.

‰

The water pump(s) operates correctly
when turned ON at the controller.

‰

The Dialflow water bleed rate is
adjusted to suit local water
conditions.

‰

The Dump Valve (option). The tank
drains correctly when unit turns off.

‰

The fan deck is correctly located and
the fan blade spins freely.

‰

The mains and control wiring are
complete and the circuit breaker is
turned ON.

‰

The fan operates correctly on all
speeds.

‰

Water distribution is even with the
filter pads fitted and the air
conditioner operating pump and fan.

‰

All Controller functions for the
appliance operate.

‰

Fan motor current draw.

Ductwork and general

‰

All ductwork is completed to plan,
correctly supported and airtight.

‰

Air distribution checked, dampers are
adjusted and all outlets correctly
adjusted and wiped clean.

‰

All roof penetrations are fully sealed
and watertight.

‰

Man-hole cover replaced.

Site

‰

All rubbish has been removed from
inside and on the roof.

Customer Hand Over

You have explained the following to the
customer.

‰

The operation of the Controller.

‰

Adequate exhaust is required for the
effective cooling. Air exit areas
should be at least 0.5 square meters
per 1000 litres of air.

‰

The operation of the bleed or
dumping system and it’s importance
to operate all the time

‰

Maintenance requirements