Water Connections

Bonaire Commercial / Industrial EAC

W

ATER

I

NSTALLATION

A permanent water supply is required to be connected to the float valve, for float valve
installation. Units have been type test certified to MP52, Spec101. Certificate No.8663.

700C – 1500C

Connecting the Water Supply

• The water supply pipe work and connection

to the air conditioner must be installed by a
licensed plumber and conform to all local
regulations. The ball valve connection is
inside the unit.

• Ensure copper inlet pipe is secured to

prevent movement of the float valve.

• The supply pipe should be copper pipe or

similar approved. A manual water-isolating
tap must be installed on the supply pipe near
the unit for ease of maintenance. Do not use
duo or non-return valves of any kind.

NOTE: Non return type valves can have

and effect on the operation of the
water solenoid valves. Lock up
and damage can be caused
.

• Fit water supply tap close to the unit to assist in routine servicing.

• Before connecting the supply pipe flush it of any swarf or debris that may cause the

float valve to leak.

NOTE: In areas where water pipes freeze, provisions will be needed to drain

the water piping to prevent damage to the air conditioner.