6.8 Multiple Boiler Venting Installation

• Multiple boiler application boiler shall be vented

individually.

• Follow guidelines as described in figures 6-1 through

6-7.

6.9 Condensate Piping

• Use materials acceptable to authority having jurisdiction.

In absence of such authority:

• USA - PVC or CPVC per ASTM D1785/D2845 Cement

or primer per ASME D2564 or F493.

• Canada - CSA or ULC certified PVC/CPVC pipe,

fittings and cement.

• Attach condensate trap provided with boiler and field

sourced piping to condensate drain at bottom of boiler.

See figure 6-17.

• Slope condensate drain pipe minimum 1/4" per foot

(21mm/m) away from boiler.

• Use field source condensate pump if boiler located

below disposal point.

• Field source condensate neutralizing kit as required

by authority having jurisdiction or for environmentally

friendly condensate disposal.

FIGURE 6-17 Condensate Drain

Condensate Trap

(field installed)

on condensate drain

pipe

End must be

left open.

Do not place in environment

with temperatures below

freezing. Condensate outlet

will block if condensate

freezes.

6 - COMBUSTION AIR AND VENT PIPING

Advertising