9 - START UP PROCEDURE

Natural Gas and Propane

3.

Measure CO

2

at high fire and compare to table.

Adjust CO

2

if needed using figure 9-3. See figure

9-5 for combustion air analyzer port.

High Fire Combustion - 50/75/100/15/200 MBH

Gas

CO

2

Design

Target

CO

Flame

Signal

Min. Max.

μA

Natural Gas

9.0 9.5%

9.5%

<200ppm

6.5-7.5

Propane

10.0 11.0

11.0%

Low Fire Combustion - 50/75/100/15/200 MBH

Gas

CO

2

Design

Target

CO

Flame

Signal

Min. Max.

μA

Natural Gas

8.8 9.3%

9.0%

<100ppm

>3.3

Propane

9.8

10.5

10.0%

NOTICE

Contact Technical Support @ 800-325-5479 for

additional information or assistance.

Natural Gas only

4.

Measure input. Compare to table 11. Continue to

measure input and CO

2

until both measured values

are within range specified in tables

.

Propane Gas

Most propane systems do not have flow meters.

1.

Check CO

2

. Propane should be between 10% and

11.0%.

• If CO

2

is low increase gas flow following figure

9-3.

• If CO

2

is high decrease gas flow following figure 9-3.

1/4" Flat Head

Screwdriver

FIGURE 9-3 Gas Valve - Models

• To increase gas flow turn 'throttle' left or counter

clockwise

.

• To decrease gas flow turn 'throttle' right or

clockwise .

• Limit adjustment to one turn and retest.

Verify Burner, Proper Operation

1.

Inspect burner flame through Sight Glass. See

figure 11-1.

2.

Operate boiler through several heating cycles,

including domestic hot water, if used. Verify proper

operation.