INSTALLATION

- 21 -

A - Central Heating Isolation Valve

B - Domestic Hot Water

C - Gas Service Isolation Valve

D - Domestic Cold Water

E - Washers (not shown)

F - Condensate Connection

G - Double check inlet valve

H - Safety Discharge Valve

SECURING

SCREW

Numbers 1 - 5

show the sequence to be used

when tightening to copper tails.

13926

Diagram 8.2

Diagram 8.1

1481

1

8 Boiler Fixing

8.1 Boiler Hanging

IMPORTANT: With regards to the Manual Handling Operations,

1992 Regulations, the following lift operation exceeds the

recommended weight for a one man lift, refer to section 16

Manual Handling.

IMPORTANT: Direct Rear Flue only - The direct rear flue must

be fitted before hanging the boiler, refer to sections 10.11 to

10.13, and the rear outlet cover plate should be removed.

The appliance and jig (pre-filled) may contain a small amount of

water, place a water container beneath the boiler connections.

Make sure the isolation valves are closed before disconnecting

the blanking plugs and discarding the jig plate.

Position the sealing washers supplied in the Loose Items pack,

as shown in diagram 6.1.
Lifting the boiler into position, lean the top of the boiler slightly

to the wall and position just above the hanging bracket. Lower

the boiler slowly, push back and engage onto the hanging

bracket making sure the boiler is located over the retaining

bosses, secure with screw provided, see diagram 8.1.

Remove the protective caps.

Engage the fixing jig connections, ensuring that the previously

positioned washers have not been disturbed.

There are flats on the body of the valves for locating a spanner

to aid tightening to copper tails using the tightening sequence

shown in diagram 8.2.

Make good the final connections.