4 installation – Glow-worm Hideaway 80BFF User Manual

Page 10

Advertising
background image

10

221958B

Diagram 4.2

10051

General Installation Notes

The appliance pack contains :-

Boiler

Fan connector

Casing panels, packed seperately.

Loose items fittings pack, see list in pack.

The flue is supplied seperately.

NOTE: The rear flue option kit Part No. 425861 is available,
which consists of wall cover plates, for replacement Hideaway
balanced flue appliances.

Before installation of the boiler make sure that the location
selected is in accordance with the requirements of Section 1.7.

4.1 Unpacking

The boiler casing panels are packed separately within the main
carton and are designed to enable gas and water connections
to be made before fitting the casing panels.

The casing brackets, flue restrictor, distributor tube and other
loose items, are in the fittings pack.

NOTE:

To make a neat finish to the flue outlet a flue collar kit, part No.
900850, with instructions, is available, see diagram 6.4.

If required an optional wall liner kit, part no. 900862, is available
complete with instructions.

All flue assemblies are designed for internal installation.

Make sure that the ductings do not slope down towards the
boiler.

Diagram 4.1

9867

9868

4.2 Flue Position and Length

Select the boiler location, with due regard to the flue length and
terminal position, see diagrams 3.1 and 4.1.

For a wall thickness up to 300mm, provided that the optional
wall liner kit is used, the flue can be fully installed from the
inside.

For a wall thickness of over 300mm the external flue hole will
need to be made good from the outside, this also applies if you
use the flue kit without the optional wall liner kit, irrespective of
wall thickness.

4 Installation

REAR STD.
REAR

75

95

510

MINIMUM

WALL

THICKNESS

MINIMUM

FLUE

LENGTH

MAXIMUM

FLUE

LENGTH

FLUE

PACKS

NOTE :
IF IT IS NECESSARY TO CUT THE DUCTS
TO ACHIEVE THE "FLUE LENGTH" MAKE SURE
THAT THE OVERLAPS ARE AS FOLLOWS :-
THE OVERLAP FOR AIR DUCT = 25mm
THE OVERLAP FOR FLUE DUCT = 50mm

FLUE & AIR DUCT LENGTH = A + 15 + 3

387

194

700

115

BOILER
OUTLINE

FRONT VIEW

*

INCREASE TO 30mm IF A FLUE COLLAR IS ADDED

*

Advertising