COMPACT - 50 HZ INSTALLATION MANUAL

Condensate Overflow - fault is recognized when the

impedance between this line and 24 VAC common or chassis

ground drops below 100K ohms for 30 seconds continuously.

Freeze Detection - set points shall be either -1.1°C or

-9.4°C. When the thermistor temperature drops below

the selected set point, the control shall begin counting

down the 30 seconds delay. If the thermistor value rises

above the selected set point, then the count should reset.

The resistance value must remain below the selected set

point for the entire length of the appropriate delay to be

recognized as a fault. This fault will be ignored for the initial

2 minutes of the compressor run time.

Over/Under Voltage Shutdown - An over/under voltage

condition exists when the control voltage is outside the

range of 18 VAC to 30 VAC. If the over/under voltage

shutdown lasts for 15 minutes, the lockout and alarm relay

will be energized. Over/under voltage shutdown is self-

resetting in that if the voltage comes back within range

of 18 VAC to 30 VAC for at least 0.5 seconds, then normal

operation is restored.

Operation Description

Power Up - The unit will not operate until all the inputs and

safety controls are checked for normal conditions. The unit

has a 5 to 80 second random start delay at power up. Then

the compressor has a 4 minute anti-short cycle delay after

the random start delay.

Standby In standby mode, Y1, Y2, W, DH, and G are not

active. Input O may be active. The blower and compressor

will be off.

Heating Operation

Heating, 1st Stage (Y1) - The blower is started on low

speed immediately and the compressor is energized

10 seconds after the Y1 input is received. The variable

speed ECM blower motor is switched to medium speed 15

seconds after the Y1 input.

Heating, 2nd Stage (Y1, Y2) - The compressor will be

staged to full capacity 20 seconds after Y2 input is

received. The variable speed ECM blower will shift to high

speed 15 seconds after the Y2 input is received.

Heating, 3rd Stage (Y1, Y2, W) - The first stage of electric

heat is energized 10 seconds after the W command is

received. If the demand continues the second stage of

electric heat will be energized after 5 minutes.

Emergency Heat (W) - The blower will be started on low

speed, 10 seconds later the first stage of electric heat will

be turned on. 5 seconds after the first stage of electric

heat is energized the blower will shift to high speed. If the

emergency heat demand is not satisfied after 2 minutes the

second electric heat stage will be energized.

Blower (G) - The blower will start immediately upon

receiving a thermostat G command. If there are no other

commands from the thermostat the variable speed ECM

will run on low speed until the G command is removed.

Regardless of blower input (G) from the thermostat, the

blower will remain on low speed for 30 seconds at the end

of each heating cycle.

Cooling Operation

In all cooling operations, the reversing valve directly tracks

the O input. Thus, anytime the O input is present, the

reversing valve will be energized.

Cooling, 1st Stage (Y1,O) - The blower is started on low

speed immediately and the compressor is energized 10

seconds after the Y1 input is received. The variable speed

ECM blower motor is switched to medium speed 15 seconds

after the Y1 input.

Cooling, 2nd Stage (Y1, Y2, O) - The compressor will be

staged to full capacity 20 seconds after Y2 input was

received. The variable speed ECM blower will shift to high

speed 15 seconds after the Y2 input was received.

Blower (G) - The blower will start immediately upon

receiving a thermostat G command. If there are no other

commands from the thermostat the variable speed ECM

will run on low speed until the G command is removed.

Regardless of blower input (G) from the thermostat, the

blower will remain on low speed for 30 seconds at the end

of each heating, cooling, emergency heat, and reheat cycle.

Dehumidification (Y1, O, DH or Y1, Y2, O, DH) - When a

DH command is received from the thermostat during a

compressor call for cooling the variable speed ECM blower

speed will be reduced by 15% to increase dehumidification.

Emergency Shutdown - Four (4) seconds after a valid ES

input, P2-7 is present, all control outputs will be turned off

and remain off until the emergency shutdown input is no

longer present. The first time that the compressor is started

after the control exits the emergency shutdown mode,

there will be an anti-short cycle delay followed by a random

start delay. Input must be tied to common to activate.

Continuous Blower Operation - The blower output will

be energized any time the control has a G input present,

unless the control has an emergency shutdown input

present. The blower output will be turned off when G input

is removed.