CLW QUAD SERIES CHILLER INSTALLATION MANUAL

General

System piping should be kept as simple as possible to

minimize the pressure drop, but hand valves should be field

installed to facilitate unit servicing. The piping installation

should provide service personnel with the ability to measure

and/or monitor water temperatures and pressures.

Source and load fluid connections are provided with 4-inch

[10.2cm] Victaulic grooved nipples. Each nipple will also

have a PT port installed for test and balance purposes.

It will be the installing contractor’s responsibility to

adequately support incoming piping to avoid damage to the

unit’s piping or heat exchangers. The water lines should be

routed so as not to interfere with access to the unit.

Field Connected Water Piping

For any installation where the transmission of vibration

through the piping connections could cause unacceptable

noise levels in occupied spaces it is important to provide

adequate vibration damping. One method is to use the

optional Adapter Hose Kit (kit number TKC16S-4). This Kit

consists of four pieces of a braided stainless steel flexible

hose with a 4” Victaulic connection on one end and a 4”

MPT connection with pipe union on the other. Overall length

of each piece is 18”.

NOTE: Units are factory run-tested using propylene

glycol. Prior to connecting piping to unit, thoroughly flush

heat exchangers.