Venting installation instructions, Installation planning, Continued – Desa (V)TC36NE SERIES User Manual

Page 10

Advertising
background image

www.desatech.com

116234-01F

10

INSTALLATION pLANNING

There are two basic types of direct-vent in-

stallation:

• Horizontal Termination

• Vertical Termination
Horizontal Termination Installation
IMPORTANT:

Horizontal square terminations

require only inner portion of wall firestop. Hori-

zontal installations using round termination require

exterior portion of wall firestop (see Figure 14,

page 12).

1. Set the fireplace in its desired location and

determine the route your horizontal venting

will take. Do not secure the fireplace until

all venting has been installed. Some installa-

tions require sliding the fireplace in and out

of position to make final venting connections.

Figures 14 through 18 on pages 12 through

14 show different configurations for venting

with horizontal termination that will help

you decide which application best suits your

installation. Check to see if wall studs or roof

rafters are in the path of your desired venting

route. If they are, you may want to adjust the

location of the fireplace.

2. Direct vent pipe sections and components are

designed with special twist-lock connections.

Twist-Lock procedure:

The female ends of the

pipes have locking lugs (indentations). These

lugs will slide straight into matching slots on

the male ends of adjacent pipes. Push pipe sec-

tions together and twist one section clockwise

approximately one-quarter turn until the sections

are fully locked (see Figure 8). Note: Horizontal

runs of vent must be supported every three feet.

Use wall straps for this purpose.

3. Use a 45° elbow to connect venting system

to fireplace flue collar. The elbow is designed

to be twist-locked onto the flue collar as

described in step 2. IMPORTANT: Do not

attempt to alter the configuration of the elbow

by cutting, twisting, bending, etc.

4. Assemble the desired combination of pipe and

elbows to the fireplace flue collar. If there are

long portions of venting run, pre-assembled

pipe sections may be installed as subassem-

blies for convenience.

VENTING INSTALLATION

INSTRUCTIONS

Continued

Figure 8 - Vent Pipe Connections

Female
Locking Lugs

Male
Slots

(Framing

Detail)

10

3

/

4

"

10

3

/

4

" Inside Framing

10

3

/

4

"

8

1

/

2

"

Vent Opening

Combustible Wall

Vent Opening

Noncombustible Wall

Figure 9 - Vent Opening Requirements

Center of
Hole

5. Carefully determine the location where the vent

pipe assembly will penetrate the outside wall.

The center of the hole should line up with the

center-line of the horizontal vent pipe. Mark the

wall for a 10

3

/

4

" x 10

3

/

4

" square hole. Cut and

frame the square hole in the exterior wall where

the vent will be terminated. If the wall being

penetrated is constructed of noncombustible

material, such as masonry block or concrete,

a 8

1

/

2

" hole with zero clearance is acceptable

(see Figure 9).

Advertising