Redundant System Installation
CST-5005 C-Band Satellite Terminal
3–20
Rev. 1
4. Position the antenna waveguide in place on the RF IN connector, and install the
1/4-20 bolts, 1/4” split lockwashers, 1/4” flat washers, and 1/4-20 nuts.
Do not tighten the bolts at this time.
ANTENNA
LNA
NUT
SPLIT
WASHER
FLAT WASHER
SPLIT WASHER
BOLT
5. After all the bolts, washers, and nuts have been installed, tighten them according
to the following illustrated sequence.
1
2
3
4
5
6
7
8
9
10
6. Remove the plastic covers from all the connectors, and attach the appropriate
cables.
3.4 RSU-503 Installation
Refer to the EFData RSU-503 Redundancy Switch Unit Installation and Operation
Manual.
3.5 External Connections
Refer to Section 2.5 for external connections information.