Commissioning, Operation – Flowserve NRG 26-40 User Manual

Page 22

Advertising
background image

22

Turn on power for level switch NRS 2-40 / level controller NRR 2-40.

Commissioning

Check whether the level electrode NRG 26-40 and the corresponding system components NRS 2-40 /

NRR 2-40 have been wired according to wiring diagram

Fig. 11.

Check wiring

Apply mains voltage

Operation

Operation in conjunction with switching controller NRS 2-40 in (pressurised) hot water installations and

steam plants to TRD 40, TRD 602, TRD 604, EN 2952, EN 2953 or according to national regulations.

Level electrode with CAN bus

Note

■

To analyse and eliminate malfunctions refer to “Fault finding list for troubleshooting” on

pages 23 - 24.

If the liquid level changes considerably over a short period of time during operation, the attenuation

setting of the level signal should be modified. The default attenuation value set at our works is 9

seconds.
. Undo screws

E and remove housing cover G.

2. Write down the node ID and the baud rate. Pull out the CAN bus connector.

2. Set code switch S  to ON, S 2 – S 7 to OFF.

S 

S 2

S 3

S 4

S 5

S 6

S 7

ON

OFF

OFF

OFF

OFF

OFF

OFF

3. Use code switches S 8 – S 0 to set the attenuation value.

S 8

S 9

S 0

Attenuation [s]

OFF

OFF

OFF

3

ON

OFF

OFF

5

OFF

ON

OFF

7

ON

ON

OFF

9

OFF

OFF

ON

5

ON

OFF

ON

9

OFF

ON

ON

25

ON

ON

ON

29

Adjusting the attenuation of the level controller