Commissioning, Operation – Flowserve NRG 26-40 User Manual

Page 22

Advertising
background image

22

Turn on power for level switch NRS 2-40 / level controller NRR 2-40.

Commissioning

Check whether the level electrode NRG 26-40 and the corresponding system components NRS 2-40 /

NRR 2-40 have been wired according to wiring diagram

Fig. 11.

Check wiring

Apply mains voltage

Operation

Operation in conjunction with switching controller NRS 2-40 in (pressurised) hot water installations and

steam plants to TRD 40, TRD 602, TRD 604, EN 2952, EN 2953 or according to national regulations.

Level electrode with CAN bus

Note

To analyse and eliminate malfunctions refer to “Fault finding list for troubleshooting” on

pages 23 - 24.

If the liquid level changes considerably over a short period of time during operation, the attenuation

setting of the level signal should be modified. The default attenuation value set at our works is 9

seconds.
. Undo screws

E and remove housing cover G.

2. Write down the node ID and the baud rate. Pull out the CAN bus connector.

2. Set code switch S  to ON, S 2 – S 7 to OFF.

S 

S 2

S 3

S 4

S 5

S 6

S 7

ON

OFF

OFF

OFF

OFF

OFF

OFF

3. Use code switches S 8 – S 0 to set the attenuation value.

S 8

S 9

S 0

Attenuation [s]

OFF

OFF

OFF

3

ON

OFF

OFF

5

OFF

ON

OFF

7

ON

ON

OFF

9

OFF

OFF

ON

5

ON

OFF

ON

9

OFF

ON

ON

25

ON

ON

ON

29

Adjusting the attenuation of the level controller