2.3.2 RS-485 End-of-Line Wiring and Termination
RS-485 installations require specialized wiring. A number of manufacturers make

cable especially for this wiring standard (EIA-485), (e.g. Belden 9841). This is a

twisted, shielded, balanced pair, 24 awg, 120 ohm. In order to prevent signal

bounce-back and other distortions, it is necessary to provide a balancing resistor

across both ends of the wire. The M-17 supplies this resistor on board, and it is

chosen using a jumper at JP2.

Figure 4 - RS-485 End-of-Line Termination (JP2)

2.4 Gas Calibration

Calibration should not vary significantly over a period of years; however, it is best

to perform a verification calibration after installation, and at one-year intervals

thereafter. All units are factory calibrated.

2.4.1 Equipment Required

Zero air, (must contain oxygen).

Appropriate span gas, typically about 50% LEL

Pressure and Flow Limiting Regulator(s) 0.4to 0.8 lpm (0.8 to 1.6 scfh)

Tubing and bayonet adapter.

Figure 5 - Calibration Gas Bayonet Adapter

2.4.2 Calibration Procedure

Response of this sensor to gas is quite rapid, and the signal should be adequately

stable for adjustment in less than one minute. It is best to allow one hour warm-up

and stabilization time before calibrating.