19. Press <ENTER> once more to save the new value.
20. Press <ESC> to end the initialization process.
21. The message "To start press <ENTER>" is
displayed.
The Sunny Island 3324/4248 can now be started and the loads supplied from
the batteries.
If however the system is to be operated with the public grid, a generator or a
PV system with Sunny Boys, then read section 8 on and make the following
additional parameter settings.
SMA Technologie AG also recommends the installation and use of a load
shedding system to protect the batteries (see section 8.6 "Automatic Load
Shedding Setting" (Page 80)).
During the "Init" initialization phase, the Sunny Island 3324/4248 performs a
number of self-tests to ensure that no faults exist in the system. Once these tests
are finished, the display normally shows the message "To init system press
<ENTER>". If the inverter detects a fault and shows this in the display, then the
fault must be corrected before continuing with first commissioning. Use the
information in section 18 "Troubleshooting/Problem Solving" (Page 143).
Once all corrective measures have been taken, switch off the Sunny Island
3324/4248, then wait 30 seconds before beginning the first commissioning
process anew.
To start
press <ENTER>