9

disk or O-ring seat are referenced in Figure 9, part key

numbers unique to the 1000 psig (69,0 bar) maximum

inlet regulator are referenced in Figure 11, and part

key numbers for a Type 61HP (extra high pressure)

pilot is referenced in Figure 12.
1. Access to all internal actuator parts can be gained

without removing the main valve body from the

line. Disconnect the loading tubing from the

upper casing.

CaUTIOn

If the regulator has an indicator

assembly, perform the following step

carefully to avoid bending the travel

indicator stem (key 103, Figure 6).

note

The O-rings and gaskets (keys 111 and

108, Figure 6) in the indicator assembly

are static seals and need not be

disturbed, unless they are leaking.

2. Remove the four cap screws (key 58, Figure 9) and

lift off the spring case (key 1, Figure 9). Remove

the travel indicator stem, if any, by unscrewing the

indicator stem adapter (key 101, Figure 6).
3. Remove the main spring seat (key 2, Figure 9)

and main spring (key 3, Figure 9).
4. Remove the 12 cap screws (key 12, Figure 9)

and hex nuts (key 13, Figure 9), and lift off the

upper casing.
5. Remove the diaphragm (key 11, Figure 9) and

diaphragm plate (key 10, Figure 9) by tipping it so

that the lever (key 9, Figure 9) slips out of the

pusher post (key 8, Figure 9).
6. Separate the diaphragm and diaphragm plate by

unscrewing the diaphragm rod (key 4, Figure 9)

from the pusher post. Inspect the diaphragm

(key 11, Figure 9) and pusher post gasket (key 7,

Figure 9). Either part must be replaced if it is

damaged or no longer pliable.
7. If the unit has a stem seal O-ring (key 64,

Figure 7 or 11), this O-ring may be replaced by

removing the retaining ring or cotter pin (key 28,

Figure 9) and disconnecting the lever from the

valve carrier (key 26, Figure 9 or 11), removing

the union nut (key 14, Figure 9 or 11),

disconnecting the pilot supply tubing (key 24,

Figure 9 or 11), and sliding the lower casing

(key 29, Figure 9) away from the valve body

(key 17, Figure 9), with a disk or O-ring seat, the

valve carrier must be pulled out of the lower

casing to gain access to the O-ring. Another

O-ring, held captive by the pressed-in bushing, is

part of the lower casing assembly on a stem seal

unit and normally does not require replacement.
8. If clogging is suspected in the upstream regulator

passages, disconnect the pilot supply tubing

(key 24, Figure 9 or 11), remove the filter assembly

(key 75, Figure 9), and blow through it to check

for filter clogging. If necessary, to clean or replace

filter parts in a standard P590 Series filter

assembly, remove the following as shown in

Figure 10: filter body (key 1), machine screw

(key 4), spring washer (key 6), gasket (key 7),

washer (key 5), and filter element (key 2). Upon

reassembly, one of the flat washers must go

between the filter element and filter head (key 3)

and the other must go between the filter element

and gasket.
9. If the lower casing was removed, install a new body

gasket (key 16, Figure 9) and, with a disk or O-ring

seat, slide the valve carrier into the casing. Then

slide the entire assembly into the valve body (disk

or O-ring seat) and secure with the union nut.

Secure the lever to the valve carrier with the

retaining ring or cotter pin.
10. Loosely reassemble the diaphragm and

diaphragm plate so that the bolt holes and

loading connection hole in the diaphragm can

be properly aligned with the corresponding

holes in the casing when the lever is fitted

properly into the pusher post. When this

orientation is made, install the collar (key 6,

Figure 9) and tighten the diaphragm rod into the

pusher post (key 8, Figure 9).
11. In order for the regulator to operate properly, the

assembled collar, diaphragm, diaphragm plate,

pusher post, and diaphragm rod must be

mounted on the ball of the lever so that the

pusher post (key 8, Figure 9) orientation is as

shown in Figure 9.
12. Install the upper casing and secure it to the

lower casing with the twelve cap screws torque

580 to 920 inch-pounds (65,5 to 104 N•m) and hex

nuts. Put lower casing back on body and install

union nut.