The base should also be located where no runoff of
water from higher ground can collect in the unit.

R

OOF

TOP

I

NSTALLATIONS

O

NLY

:

To avoid possible property damage or personal injury,
the roof must have sufficient structural strength to carry
the weight of the unit(s) and snow or water loads as
required by local codes. Consult a structural engineer
to determine the weight capabilities of the roof.

The unit may be installed directly on wood floors or
on Class A, Class B, or Class C roof covering material.

To avoid possible personal injury, a safe, flat surface
for service personnel should be provided.

As indicated on the unit data plate, a minimum
clearance of 36” to any combustible material is
required on the furnance access side of the unit. All
combustible materials must be kept out of this area.

This 36” clearance must also be maintained to insure
proper combustion air and flue gas flow. The
combustion air intake and furance flue discharge must
not be blocked for any reason, including blockage by
snow.

Adequate clearances from the furnace flue discharge
to any adjacent public walkways, adjacent buildings,
building openings or openable windows must be
maintained in accordance with the latest edition of
the National Fuel Gas Code (ANSI Z223.1)

Minimum horizontal clearance of 48” from the furnace
flue discharge to any electric meters, gas meters,
regulators and relief equipment is required.

U

NIT

P

RECAUTIONS

Do not stand or walk on the unit.

Do not drill holes anywhere in panels or in the base
frame of the unit. Unit access panels provide
structural support.

Do not remove any access panels until unit has been
installed on roof curb or field supplied structure.

Do not roll unit across finished roof without prior
approval of owner or achitect.

Do not skid or slide on any surface as this may
damage unit base. The unit must be stored on a
flat, level surface. Protect the condenser coil
because it is easily damaged.

R

OOF

C

URB

I

NSTALLATIONS

O

NLY

:

Curb installatons must comply with local codes and should
be done in accordance with the established guidelines of the
National Roofing Contractors Association.

Proper unit installation requires that the roof curb be firmly
and permanently attached to the roof structure. Check for
adequate fastening method prior to setting the unit on the
curb.

Full perimeter roof curbs are available from the factory and
are shipped unassembled. Field assembly, squaring, level-
ing and mounting on the roof structure are the responsibility
of the installing contractor. All required hardware necessary
for the assembly of the sheet metal curb is included in the
curb accessory.

WARNING

T

O PREVENT POSSIBLE EQUIPMENT DAMAGE, PROPERTY DAMAGE, PERSONAL

INJURY OR DEATH, THE FOLLOWING BULLET POINTS MUST BE OBSERVED

WHEN INSTALLING THE UNIT.

Sufficient structural support must be determined prior
to locating and mounting the curb and package unit.

Ductwork must be constructed using industry
guidelines. The duct work must be placed into the
roof curb before mounting the package unit. Our full
perimeter curbs include duct connection frames to be
assembled with the curb. Cantilevered type curbs
are not available from the factory.

Curb insulation, cant strips, flashing and general
roofing material are furnished by the contractor.

The curbs must be supported on parallel sides by roof mem-
bers. The roof members must not penetrate supply and re-
turn duct opening areas as damage to the unit might occur.

NOTE: The unit and curb accessories are designed to allow
vertical duct installation before unit placement. Duct
installaton after unit placement is not recommended.

A

LL

CURBS

LOOK

SIMILAR

. T

O

AVOID

INCORRECT

CURB

POSITIONING

,

CHECK

JOB

PLANS

CAREFULLY

AND

VERIFY

MARKINGS

ON

CURB

ASSEMBLY

. I

NSTRUCTIONS

MAY

VARY

IN

CURB

STYLES

AND

SUPERSEDES

INFORMATION

SHOWN

.

CAUTION

See the manual shipped with the roof curb for assembly and
installation instructions.

CLEARANCES