8 commissioning the sunny mini central, Commissioning the sunny mini central – SMC Networks Sunny Mini Central SMC 5000A User Manual

Page 51

Advertising
background image

SMA

Technologie AG

Commissioning the Sunny Mini Central

Installation Guide

SMC50A_60A-IEN073320

Page 51

8 Commissioning the Sunny Mini Central

Proceed with commissioning the Sunny Mini Central only after:

the housing cover is securely screwed shut,

the DC cables (PV strings) are fully connected and the unused DC plug connectors
on the bottom of the housing are closed using the protective caps,

the Electronic Solar Switch is securely attached,

the AC (power) cable is fully connected and

the line circuit breaker is laid out correctly.

Commissioning Procedure

Step

Instruction

1

First of all, switch the line circuit breaker to
the "on" position.

2

Now look at the LED or the display to check
whether the Sunny Mini Central is in a fault-
free operating status. If this is the case,
commissioning was successfully completed.
If the Sunny Mini Central shows other
messages or blink codes than those
described below, see the operating manual
of the Sunny Mini Central for their precise
meaning and possible solutions.

On!

Advertising
This manual is related to the following products: