B-3

OPERATION

B-3

PIPELINER® 200D KUBOTA

IDLER OPERATION

Start the engine with the “Idler” switch in the “High”

position. Allow it to run at high idle speed for several

minutes to warm the engine. See Specifications for

operating speeds.

The idler is controlled by the “Idler” toggle switch on

the welder control panel. The switch has two posi-

tions as follows:

1. In the “High” position, the engine control unit

increases the engine to high idle speed.

2. In the “Auto” / position, the idler oper-

ates as follows:

a. When welding or drawing power for lights or tools

(approximately 100 watts minimum) from the recep-

tacles, the engine operates at high idle speed.

b. When welding ceases or the power load is turned

off, a preset time delay of about 15 seconds starts.

This time delay cannot be adjusted.

c. If the welding or power load is not re-started before

the end of the time delay, the engine control unit

reduces the engine to low idle speed.

AUXILIARY POWER

1.75 kVA of 120 V DC auxiliary power is availiable at

the receptacle located on the control panel.

When the High Speed Adjustment knob is in the MIN

position, the voltage of the DC auxiliary output may be

reduced to below the rating on the nameplate of the

machine. It is recommended that the High Idle Speed

Adjustment knob should be in the MAX position when

using the DC auxiliary output.

Always replace blown fuse with type rated for DC volt-

age (i.e. Cooper Bussmann Inc. Model LP-CC-15 or

Littlefuse Model CCMR-15.

PIPELINER® 200D WITH KUBOTA V2403M DIESEL ENGINE

TYPICAL FUEL CONSUMPTION DATA

Low idle (1400 RPM )

.39 gal/hr (1.46 ltrs/hr )

No Load

High idle ( 1600 Rpm )

.53 gal/hr (2.00 ltrs/hr )

No load

200 Amps @ 28 Volts

.90 gal/hr (3.42 ltrs/hr )

Auxiliary Power

1,750 Watts

.54 gal/hr (2.04 ltrs/hr)